We use cookies to collect anonymous data to help us improve your site browsing experience.

Click 'Accept all cookies' to agree to all cookies that collect anonymous data. To only allow the cookies that make the site work, click 'Use essential cookies only.' Visit 'Set cookie preferences' to control specific cookies.

Your cookie preferences have been saved. You can change your cookie settings at any time.

Search

What can we help you with today?

Skip to main

Case: CA72/23

FES Limited v HFD Construction Group Limited

Watch previous livestream hearing

FES Limited v HFD Construction Group Limited

Case: CA72/23

Friday, 20 September 2024

10:30 to 13:00 then 14:00 until conclusion

Welcome to Court of Session Live

This is an archive of a livestream. Find out about restrictions on livestreaming.

About this case

Case name

FES Limited v HFD Construction Group Limited

Case reference number

CA72/23

Date of hearing

Friday 20 September 2024

Time of hearing

10:30 to 13:00 then 14:00 until conclusion

Division

First Division

Judges

  • Lord President
  • Lady Wise
  • Lord Beckett

Agents and Counsel

For the Reclaimers (the appellants) (FES Ltd):

  • Agents: Brodies LLP
  • Counsel: Gavin MacColl KC

For the Respondents (HFD Construction Group Ltd)

  • Agents: Dentons UK and Middle East LLP
  • Counsel: Paul O'Brien KC 

Case description

In 2020, HFD Construction entered into a contract with FES Ltd, in terms of which FES Ltd agreed to complete a fit out of a new Grade A office building at 177 Bothwell Street, Glasgow. The contract took the form of the Standard Building Contract with Quantities for use in Scotland (SBC/Q/Scot) (2016 Edition), with some amendments.

During the project, the construction work was delayed for various reasons, including site closures due to the COVID-19 pandemic. Clause 4.20.1 of the contract provided that FES Ltd could recover loss and expense for certain delays encountered during the contract works, subject to compliance with clause 4.21. Clause 4.21 contained notice provisions.

FES wished to claim for loss and expense under clause 4.20.1, but had not complied with the notice provisions. HFD contended that this meant that FES was not entitled to claim. FES referred the dispute to adjudication.

An adjudicator issued his decision on 10 March 2023. He agreed with HFD’s argument. He found that the giving of notice under clause 4.21.1 was a condition precedent (a prerequisite) of an entitlement to claim for loss and expense under clause 4.20.1. Since FES had not given the required notice, they had no entitlement to claim.

FES raised the present action, in which they contend that the adjudicator erred in his interpretation of clauses 4.20 and 4.21. They seek a declaration by the court that the notice provisions in clause 4.20 are not conditions precedent to their entitlement to reimbursement for direct loss and expense. They seek a second declaration that, since it is based on an error of law, the adjudicator’s decision, insofar as it rules out FES’s right to claim, is not binding on the parties.

Following a legal debate, the commercial judge determined the adjudicator’s decision was correct, and dismissed the action. FES Ltd appeals that decision. The First Division will hear the appeal on Friday 20 September 2024.